What priority of change request is made for non-urgent issues?

Get more with Examzify Plus

Remove ads, unlock favorites, save progress, and access premium tools across devices.

FavoritesSave progressAd-free
From $9.99Learn more

Prepare for the Garrison Test with flashcards and multiple-choice questions. Each question comes with detailed hints and explanations. Ace your exam!

The priority of change request made for non-urgent issues is classified as routine. This classification is used for changes that are not time-sensitive and can be scheduled for implementation during regular maintenance windows. Routine changes typically involve standard procedures and processes that have been established and documented, allowing them to be handled efficiently without the need for immediate action.

In a change management context, recognizing the difference between routine changes and more urgent or emergency changes is essential. Emergency changes require immediate attention due to critical situations that need to be resolved quickly to prevent outages or serious incidents. Urgent changes, on the other hand, also require timely action but may not be as critical as emergencies. Immediate changes indicate an even higher priority, signaling that they must be enacted without delay.

Thus, routine clearly addresses changes that are planned and can be carried out in a systematic way, highlighting the need for organizations to manage their change requests according to the urgency and potential impact on operations.